DEE Development Engineers Ltd is preparing for a revenue loss of ₹260 million per annum at its Muktsar plant after the Punjab government decided to rebalance tariffs for renewable energy projects. The tariff adjustment, cleared by the Punjab State Electricity Regulatory Commission (PSERC), falls under the state's efforts to provide cheap electricity to consumers and ease the burden of expensive power purchase from old pacts.
 
Revenue Impact at Muktsar Plant
DEE Development Engineers has revealed that its Muktsar unit anticipates an annualized revenue loss of ₹260 million as a result of the new, lower tariff rates set by the Punjab regulator. This change is part of a larger state effort to review and realign power purchase agreements with independent producers, especially in the renewable segment.
 
Tariff Redetermination for 8 MW Plant:
The Punjab state government, through the Punjab Renewable Energy Security, Reform, Termination and Re-determination of Power Tariff Act, 2021, has authorized PSERC to re-evaluate and re-set tariffs for current power generators. The 8 MW facility owned by DEE Development Engineers is one of those impacted, with the new tariff meant to strike a balance between consumer interests and avoiding unsustainable financial costs to the state utility.
 
Strategic and Financial Implications:
The Muktsar revenue setback is a concern for DEE Development Engineers, otherwise on a growth path with a goal of tripling revenue in the next 3–5 years to ₹2,400 crore. The company has made significant investment in new manufacturing facilities recently and has seen good profit growth in other businesses, but the tariff reset is an indication of regulatory threats in the renewable power space.
Punjab's tariff overhaul is one of a broader thrust throughout India to renegotiate costly renewable energy deals entered into in previous years in a bid to make power cheaper for end-users and ease the burden on state power utilities' financials.
 
Insight
While DEE Development Engineers is expanding and diversifying its business, the revenue decline at its Muktsar plant highlights the risks imposed on renewable energy developers by changes in regulation. The firm will have to change strategy to counter such threats as tariff resets are becoming more frequent in India's changing power landscape.
 
Source: Business Standard, Punjab Renewable Energy Security, Reform, Termination and Re-determination of Power Tariff Act, 2021, INDmoney, The Machine Maker