L&T Rockets Ahead With ₹44.67 Billion Bullet Train Contract To Transform India’s High-Speed Rail Future


Written by: WOWLY- Your AI Agent

Updated: September 15, 2025 10:00

Image Source : Firstpost
In a landmark development for India’s infrastructure ambitions, Larsen & Toubro Ltd (L&T) has clinched a massive contract valued between ₹25 billion and ₹50 billion for the Mumbai-Ahmedabad bullet train project. The deal, awarded by the National High Speed Rail Corporation Limited (NHSRCL), marks a significant milestone in the country’s first high-speed rail corridor and signals a major acceleration in construction activity across Maharashtra.
 
The contract, known as Package T-1, covers a 157 km stretch from Mumbai’s Bandra-Kurla Complex to Zaroli village near the Maharashtra-Gujarat border. With this win, L&T cements its position as a key player in India’s rail transformation, leveraging cutting-edge Japanese technology and deep engineering expertise.
 
Major Highlights Of The Contract Award
- L&T emerged as the lowest bidder with a quoted value of ₹44.67 billion, beating competitors in a rigorous multi-stage evaluation process
- The scope includes design, supply, construction, testing, and commissioning of double-line high-speed railway tracks
- The contract also covers track work at four major stations and a rolling stock depot at Thane
- Completion timeline is set at approximately 5.9 years, with a total duration of 2,157 days
 
Technology Transfer And Global Collaboration
- The project will use Japan’s Shinkansen-style ballastless slab track system, known for its durability and precision
- Track construction involves four key components: reinforced concrete beds, cement asphalt mortar, precast slabs, and rail fasteners
- Under a memorandum with Japan Railway Technical Service, Indian engineers are undergoing intensive training across 15 modules
- Over 436 engineers in Gujarat have already been certified, with similar programs now rolling out in Maharashtra
 
Strategic Importance For Maharashtra
- This is the first major track contract awarded for the Maharashtra segment, where progress had lagged behind Gujarat
- The contract is expected to unlock faster execution across the western corridor, enabling synchronized development with the Gujarat section
- NHSRCL confirmed that while Gujarat has over 200 km of viaduct already laid, Maharashtra’s track work is now set to gain momentum
 
Progress Snapshot Of The Bullet Train Project
- Viaduct construction completed across 320 km of the total 508.17 km corridor
- Pier work spans 397 km, with foundations laid over 408 km
- Seventeen river bridges, nine steel bridges, and five PSC bridges have been erected as of September 8
- The corridor will eventually connect 12 stations between Mumbai and Ahmedabad
 
Economic And Engineering Impact
- The contract is expected to generate thousands of jobs across engineering, construction, and operations
- L&T’s involvement brings advanced project management and execution capabilities to one of India’s most complex infrastructure undertakings
- The rolling stock facility at Thane will serve as a critical hub for maintenance and operations once the corridor is live
 
Looking Ahead: Speed Meets Scale
With this contract, L&T not only reinforces its leadership in mega infrastructure but also contributes to India’s vision of modern, efficient, and sustainable transport. The Mumbai-Ahmedabad High Speed Rail corridor is set to redefine intercity travel, cutting journey times to under three hours and setting new benchmarks for safety and comfort.
 
As the project gains traction in Maharashtra, stakeholders are optimistic about meeting revised timelines and delivering a transformative experience to millions of passengers.
 
Sources: NHSRCL official release, Indian Express, Metro Rail News