MBL Infrastructure Ltd has secured a favorable arbitral award worth ₹12.4 million, marking a positive turn in its ongoing efforts to resolve legacy disputes and strengthen its financial position. The award stems from a commercial arbitration case involving delayed payments and contractual breaches related to civil engineering works.
Key Highlights
-
The arbitral tribunal ruled in favor of MBL Infrastructure, awarding ₹12.4 million in compensation
-
The dispute involved nonpayment for completed fire safety installations and civil works
-
The award includes interest and partial reimbursement of legal and arbitration costs
Background and Case Details
-
The case was filed by Royale Meridian (India) Pvt Ltd against MBL Infrastructure in the Delhi District Commercial Court
-
MBL had subcontracted fire detection and wet riser system installations, but delays in site handover and payment led to arbitration
-
Despite initial setbacks, including dishonored cheques and delayed RA bill settlements, MBL successfully defended its position
Strategic Implications
-
The award adds to MBL’s legal recovery pipeline, supporting its postresolution financial restructuring
-
It reinforces the company’s credibility in contract enforcement and dispute resolution
-
The ruling may encourage other contractors and partners to settle pending claims amicably
Looking Ahead
MBL Infrastructure continues to navigate its turnaround strategy following insolvency proceedings and promoterled restructuring. Legal wins like this arbitral award offer incremental support to its balance sheet and signal improved governance and operational discipline.
Sources: Indian Kanoon, Delhi District Commercial Court Order, Economic Times, Dun & Bradstreet, Moneycontrol