Vipul Organics Ltd is making significant strides in its Sayakha greenfield pigment production facility, with Phase 1 expected to commence operations in Q3 FY 2025-26. The company has secured key regulatory approvals and is advancing rapidly with civil construction, reinforcing its commitment to expanding its pigment manufacturing capabilities.
Key Highlights:
-
Phase 1 Progress: The Sayakha plant is 60% through civil work, with August 2025 targeted for completion.
-
Regulatory Approvals Secured: Environmental clearance, building plan approval, and resource commitments have been finalized.
-
Infrastructure Development: The Effluent Treatment Plant (ETP) and administrative building are under construction, expected to be completed by October 2025.
-
Production Timeline: Pigment powder manufacturing is projected to begin between October and December 2025, aligning with Vipul Organics’ expansion strategy.
-
Strategic Importance: The facility will boost production capacity, supporting domestic and global demand for pigments.
Vipul Organics’ Sayakha facility represents a major step in modernization and efficiency, reinforcing its position in the pigment industry.