India has temporarily shut down Unit 1 of the Kudankulam Nuclear Power Plant, the country’s largest nuclear reactor, for scheduled annual maintenance. The 1,000-megawatt unit, located in Tamil Nadu, was taken offline on August 3, 2025, according to a report from the Central Electricity Authority. The shutdown is expected to last approximately 65 days and has already begun to impact power availability in southern states, particularly Kerala and Tamil Nadu.
The outage, while routine, comes at a time of heightened electricity demand and low trading volumes on power exchanges, prompting emergency procurement measures and raising concerns over short-term tariff spikes.
Key Developments Surrounding the Shutdown
- Unit 1 of Kudankulam Nuclear Power Plant was shut on August 3 for scheduled refuelling and maintenance
- The outage is expected to last 65 days, with operations resuming in early October
- Unit 2, also rated at 1,000 MW, continues to operate normally
- The shutdown has triggered emergency power purchases by Kerala and Tamil Nadu utilities
- Peak-hour procurement costs have surged to as high as ₹9.18 per unit
Impact on Regional Power Supply
1. Kerala’s Emergency Procurement
- Kerala State Electricity Board (KSEBL) filed a petition with the state regulator citing a projected 600 MW peak-hour deficit
- The board finalized short-term purchases from Tata Power at ₹8.75 per unit and Greenko Energies at ₹9.18 per unit
- The procurement covers the 7 PM to midnight slot throughout August
2. Tamil Nadu’s Contingency Measures
- Tamil Nadu Generation and Distribution Company (TANGEDCO) confirmed the outage and is monitoring demand trends
- Officials indicated that market-based sourcing may be required if demand spikes unexpectedly
- The state is also evaluating load management strategies to avoid grid stress
3. Broader Grid Implications
- Southern India’s reliance on Kudankulam for base-load nuclear power makes the outage particularly impactful
- Low volumes on power exchanges have compounded the supply crunch
- The shutdown may influence spot market prices and short-term bilateral contracts
Operational Context and Historical Precedents
- Kudankulam Unit 1 has undergone multiple planned outages since its commissioning in 2013
- The current shutdown is part of routine refuelling and safety checks mandated by the Nuclear Power Corporation of India
- Past outages have typically lasted between 45 and 70 days, depending on component upgrades and inspection schedules
- The reactor uses Russian VVER technology and is operated under federal oversight
Strategic Importance of Kudankulam
- Kudankulam is India’s largest nuclear power facility, with two operational units and two more under construction
- Unit 3 and Unit 4, each rated at 1,000 MW, are expected to be commissioned by 2026
- The plant plays a critical role in India’s energy diversification strategy, contributing to low-carbon base-load generation
- India aims to expand nuclear capacity to 100 GW by 2047, up from the current 9 GW
Outlook and Mitigation Measures
While the shutdown is temporary and part of standard maintenance protocol, its timing has amplified regional power supply challenges. Utilities are expected to rely on short-term market purchases and demand-side management to navigate the outage period. The Central Electricity Authority is closely monitoring grid stability, and further updates on the reactor’s restart schedule are anticipated in September.
Sources: Hindustan Times, Yahoo News Singapore, Central Electricity Authority, Kerala State Electricity Board.